DAY 1
START AT 11h00
•
moladi formwork is delivered to site
Area = 74m²
Mass = 550kg
Volume = 4m³
•
moladi formwork panels are assembled by
unskilled labourers to form the mould panels of
the desired house plan
STEP 1
•
Internal formwork panels are erected
•
Window frames and block-outs are positioned
within the wall cavity
•
Reinforcing bars are positioned within the cavity
to engineer specifications
STEP 2
•
Door frames and block-outs are positioned within
the wall cavity
•
External formwork panels are erected to close off
the wall cavity
•
Erection is completed in 4 hours with
4 unskilled labourers
STEP 3
•
The wall cavity is filled with 4m³ of moladi
aerated mortar by unskilled labourers
•
The pour is completed in 2 hours with
4 unskilled labourers
STEP 4
FINISH AT 17h00
•
moladi formwork panels are removed
•
moladi formwork panels are completely
removed in 2 hours with 4 unskilled labourers
STEP 1
•
Immediately after the formwork panels are
removed, the walls are painted with a
cementitious water based paint
•
Oil or acrylic based paints can be applied after
the walls have cured, or in 28 days
STEP 2
•
The engineer certified roof is installed
•
The windows and doors are installed
•
Final finishings, such as sanitary ware and
lighting are completed
•
The structure is now ready for occupation
STEP 3
START AT 07h00
FINISH AT 17h00